Hi Riccardo,
We have sum 1 > 9 Unit of 1725_
for ease we will start from Unit 1&2 (21 J.) that way the other Units will follow,
1. Time:
+ For J1, J2 unit ~25 days:
- milestone 1 (~markup1): 13 days ~ Nov 30
- milsetone 2: (~markup2) 7 days ~ Dec 9
- milestone 3(~markup3 to final): 5 days ~ Dec 16
+ For J3, J4, J5 ~20 days
+ For J6, J7, J8, J9 ~20 days
total time for project ~: 65 days
2. Fee estimates:
+ J1._ = 700 Aud,
+ J2._ = 350 Aud,
+ J3._ = 450 Aud,
+ J4._ = 650 Aud,
+ J5._ = 50 Aud,
+ J6._ = 550 Aud,
+ J7._ = 550 Aud,
+ J8._ = 300 Aud,
+ J9._ = 250 Aud,
total fee: 3850 Aud,
please consider,
Thank you!